一、好漢坡邊坡水泥護欄於113年6月監測結果有外移現象,且有落石等風險,為顧及人行安全、邊坡樓梯封閉並進行檢修及評估後續補強工法。

二、目前自強五舍下方邊坡(好漢坡)出入口已封閉,欲往自強宿舍及山下校區老師及同學請改由以下路線上下宿舍區:

    a. 國際大樓電梯

    b. 國際大樓樓梯

    c. 沿環山二道

三、為確認好漢坡周遭邊坡穩定情形,已於周遭邊坡增設傾度盤進行整體監測,至本年11月,每月監測乙次。

四、除增設傾度盤持續監測外,後續依觀測結果進行邊坡穩定性分析及工法評估,因混凝土牆體自身重量較重,未來改善評估將水泥護欄拆除,並改為裝設不鏽鋼製欄杆,依觀測及後續施工期間仍需持續封閉樓梯,後續封閉時間再由本處另行公告。​​​​​​

五、自113學年度上學期(113年9月9日)起實施新班表,上課日增加7班至自強宿舍區的班次如下:

    政大2路:由行政大樓至六期運動場 (增加1班次—14:50)

    政大3路:由行政大樓至山居學習中心 (增加6班次— 10:10、11:10、13:10、14:10、15:10、17:10)

 

 

  1. The concrete slope stabilization structure at Haohan Slope was observed to have shifted outward in June 2024, increasing the risk of falling rocks. To safeguard pedestrians, Haohan Slope has been temporarily closed for assessment, maintenance, and the development of a comprehensive stabilization plan. 
     
  2. The entrances to Haohan Slope below Zih Ciang Dormitory No. 5 have been closed. Individuals requiring access to the Zih Ciang dormitories or the Downhill Campus are advised to utilize the following alternative routes to and from the dormitory area: 

• The elevator at the International Building.
• The stairs in the International Building. 
• Mountain Circle 2.

  1. To ensure stability around Haohan Slope, inclinometers have been installed on the surrounding slopes. These devices will be used to monitor and inspect the stability of the slopes on a monthly basis until November 2024.
  1. In addition to the installation and monitoring of inclinometers, a further slope stabilization and engineering plan will be developed based on the inspection results. Given the substantial weight of the existing concrete retaining walls, the feasibility of demolishing the current concrete slope stabilization structure and replacing it with a stainless steel guardrail is being considered. Haohan Slope will remain closed throughout the construction period, with the duration of the closure to be announced by the Office of General Affairs at a later date.
  1. Campus bus services will be enhanced starting September 9, 2024. Weekday service frequency will be increased with seven additional departures. The revised schedule is as follows: 

• Route 2 (Administrative Building to Sixth Stadium): One additional departure at 14:50. 
• Route 3 (Administrative Building to Hillside Learning Lodge): Six additional departures at 10:10, 11:10, 13:10, 14:10, 15:10, and 17:10.